Huíla and Malanje Account for Four in Five Installations
Angola’s Ministry of Energy and Water reported in January 2026 that crews had installed 11,840 prepaid electricity meters in Huíla, 9,962 in Malanje, 3,242 in Benguela and 2,188 in Bengo. Together, the four counts in the ministry’s provincial installation update total 27,232 meters. Huíla and Malanje accounted for 21,802 of them, or roughly four out of every five reported across these provinces.
The ministry presented the four provinces as examples from a phased national programme that began in August 2024. The figures show where crews had fitted meters by the January update. They do not establish which province was furthest along: the ministry did not give a corresponding installation target for each of the four. Bengo’s smaller count, for example, tells readers little about the share of its planned work that crews had completed.
Why Meter Delivery and Installation Followed Different Timetables
An African Development Bank implementation report explains one condition that affected the work. The first batch of prepaid meters arrived in Angola in January 2025. In several provinces, including Bengo, Huíla and Malanje, low-voltage lines needed improvements to protect the new meters from damage. The bank reported that ENDE, Angola’s national electricity distributor, began installing those meters in September 2025.
For a distribution planner, the interval between delivery and installation matters. A meter in storage counts towards the equipment a utility has received. Putting it into service depends on the condition of the network at the customer’s premises. The bank’s account explains why crews needed to coordinate line work with meter installation. It does not establish why one province reported more installations than another.